PROJECTS

STRUCTURAL

PROJECT NAME: NORTHERN LIGHTS REGIONAL HOSPITAL

LOCATION: FORT McMURRAY, AB

DURATION: 14 MONTHS

CURRENT STATUS:  COMPLETE

UEL SUPPLIED THE STRUCTURAL AND MISCELLANEOUS STEEL FOR THE NEW HELIPAD AT THE REGIONAL HOSPITAL IN FORT McMURRAY.  WE ARE PROUD TO HAVE SUGGESTED DESIGN REVISIONS THAT PROVIDED OVER $150,000 IN COST SAVINGS FOR THE STEEL SCOPE.

PROJECT NAME: JACKSONPORT COMMERICAL BLDG 1&2

LOCATION: CALGARY, AB

DURATION: 6 MONTHS

CURRENT STATUS:  IN PROGRESS

UEL PROVIDED STEEL FOR A TWO BUILDING COMMERCIAL DEVELOPMENT IN N.E. CALGARY.  THIS FAST PACED PROJECT REQUIRED CONSIDERABLE COORDINATION WITH OUR CLIENT AND THE DESIGN TEAM.  ERECTION WAS COMPLETED AHEAD OF SCHEDULE DESPITE BEING DONE IN CALGARY’S HARSH WINTER CONDITIONS.

PROJECT NAME: GUILLEVIN

LOCATION: CALGARY, AB

DURATION: 6 MONTHS

CURRENT STATUS:  COMPLETE

THE NEW CANOPY STRUCTURE WAS PART OF A FACE LIFT FOR THIS AGING BUILDING.  WORKING WITH EXISTING BUILDINGS CAN OFTEN POSE CHALLENGES,  BUT UEL’S EXPERIENCED TEAM WAS ABLE TO ANTICIPATE THESE CONCERNS AND COMPLETE THIS PROJECT WITHOUT ISSUE.

MECHANICAL

PROJECT NAME: U OF C CRAIGIE HALL

LOCATION: CALGARY, AB

DURATION: 4 MONTHS

CURRENT STATUS:  COMPLETE

UEL SUPPLIED TWO NEW MECHANICAL SUPPORT FRAMES, COMPLETE WITH WALKWAYS AND RAILING, ABOVE AN EXISTING BUILDING ROOF AT THE UNIVERSITY OF CALGARY.

PROJECT NAME: OASIS FERTILITY

LOCATION: CALGARY, AB

DURATION: 5 MONTHS

CURRENT STATUS:  COMPLETE

CONSIDERABLE REINFORCING OF THE EXISTING ROOF STRUCTURE WAS REQUIRED PRIOR TO INSTALLING STEEL FRAMING TO SUPPORT A ROOF TOP AIR HANDLING UNIT AND GENERATOR.  CLOSE COORDINATION WAS REQUIRED TO ENSURE COMPATABILITY BETWEEN THE STEEL STRUCTURE AND MECHANICAL EQUIPMENT.

PROJECT NAME: BELL POP1

LOCATION: CALGARY, AB

DURATION: 7 MONTHS

CURRENT STATUS:  COMPLETE

GENERATOR SUPPORT STEEL WAS PROVIDED ATOP A 12 STOREY BUILDING IN DOWNTOWN CALGARY.  IN ADDITION, A CABLE TRAY SUPPORT STRUCTURE WAS INSTALLED BELOW THE 2ND FLOOR WHICH SIGNIFICANTLY INCREASED THE OWNER’S SYSTEM CAPACITY.

REINFORCING

PROJECT NAME: SAINT-JOHN WARE

LOCATION: CALGARY, AB

DURATION: 4 MONTHS

CURRENT STATUS:  IN PROGRESS

DISTRESS OF THE EXISTING CONCRETE EXPANSION JOINTS WAS NOTICED DURING AN INTERIOR RENOVATION. A  STEEL SUPPORT STRUCTURE WAS INSTALLED TO REGAIN THE STRUCTURAL INTEGRITY OF THE BUILDING.

LEASEHOLD

PROJECT NAME: SCOTIABANK

LOCATION: CALGARY, AB

DURATION: 4 MONTHS

CURRENT STATUS:  COMPLETE

INTERSTITIAL STAIRS WERE INSTALLED BETWEEN THE 15th AND 19th FLOORS OF BROOKFIELD PLACE IN DOWNTOWN CALGARY.  MATERIAL HANDLING AND ACCESS FOR THESE PROJECTS REQUIRES THOUGHTFUL CONSIDERATION AS DESIGN DETAILS SELDOM TAKE THESE INTO ACCOUNT.  THESE STAIRS ARE A FEATURE ELEMENT FOR THE TENANT AND OUR TEAM SUCCESSFULLY MET THE EXACTING STANDARDS REQUIRED.

PROJECT NAME: KENWORTH M&M BUILDING 

LOCATION: CALGARY, AB

DURATION: 2 MONTHS

CURRENT STATUS: COMPLETE

UEL DESIGNED AND INSTALLED THE STEEL FRAMING FOR THIS WASH BAY WALL IN AN EXISTING WAREHOUSE.  OUR ENGINEERING CAPABILITIES AUGMENT OUR STEEL SUPPLY SERVICE, PROVIDING A HIGHER LEVEL OF SERVICE FOR OUR CLIENTS.

MISCELLANEOUS

PROJECT NAME: CALGARY CENTRAL LIBRARY – LUKE’S CAFE

LOCATION: CALGARY, AB

DURATION: 2 MONTHS

CURRENT STATUS: COMPLETE

THE STEEL FRAMING IS THE SUPPORT STRUCTURE FOR A CAFÉ INSIDE THE RENOWNED CALGARY CENTRAL LIBRARY.  COMPONENTS OF THE STRUCTURE ARE VISIBLE TO THE PUBLIC AND FIT IN SEAMLESSLY WITH THE SURROUNDING ARCHITECTURE.

PROJECT NAME: BURGER FEDERATION

LOCATION: CALGARY, AB

DURATION: 3 MONTHS

CURRENT STATUS: COMPLETE

THIS POWDER COATED MILLWORK SUPPORT FRAME IS A FEATURE ELEMENT INSIDE THE CALGARY INTERNATIONAL AIRPORT.  AT OVER 26’ FEET IN LENGTH AND 7 FEET HIGH, IT WAS A CHALLENGE FOR OUR INSTALLERS WORKING AROUND EXISTING STRUCTURE AND SERVICES.

Send us a Message

Info

3815 56 Ave SE

Calgary, Alberta

T2C 2E4

587-471-6167

Estimating Team: Estimating@unifiedeng.ca

General Inquiries: Info@unifiedeng.ca